The below service changes to the F Train affecting Roosevelt Island and each of the stations serviced by the 63rd Street Tunnel are provided by Ms. Parker of the MTA but are subject to change and not all have been posted yet on the MTA website. A calendar graph of these dates is slated to appear in this week's Main Street WIRE.

Subsequent to the email received below, Ms. Parker, clarified that "weeknights" for purposes of these changes refers to Tuesdays through Fridays. Southbound refers to Trains Bound for Manhattan and Brooklyn and Northbound refers to trains coming from Manhattan bound for Queens.

------Original Message------

From: Deirdre Parker
To: Roosevelt Island 360
Sent: Apr 29, 2009 2:34 PM
Subject: RE: Projected Subway Service Changes

- Weeknights, from May 5th - June 16 (except May 26th), 12:01 AM - 5 AM, there will no southbound service at Roosevelt Island.

- Weekends, from May 23rd, 12:01 AM, to May 25th, 5 AM, and May 30th, 12:01 AM, to June 1st, 5 AM, there will be no southbound service at Roosevelt Island.

- Tuesdays to Fridays, June 23 to July 2nd, 12:01 AM to 5:00 AM, there will be no northbound service at Roosevelt Island.

These changes are needed to support tunnel and track work.

Deirdre K. Parker
Deputy Director, Public Affairs
MTA NYC Transit